2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,291,000 | $ | 3,555,000 | $ | 2,259,400 | |||
Estimated costs to complete as of year-end | 5,609,000 | 2,054,000 | 0 | ||||||
Billings during the year | 2,110,000 | 3,736,000 | 4,154,000 | ||||||
Cash collections during the year | 1,855,000 | 3,500,000 | 4,645,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
rev: 09_15_2017_QC_CS-99734
2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started