Required information Skip to question [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to

Required information

Skip to question

[The following information applies to the questions displayed below.]

In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:

2024 2025 2026
Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400
Estimated costs to complete as of year-end 5,041,000 2,414,000 0
Billings during the year 2,190,000 2,496,000 5,314,000
Cash collections during the year 1,895,000 2,400,000 5,705,000

Westgate recognizes revenue over time according to percentage of completion.

2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit Cash, Materials, etc. for construction costs incurred).

2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit Cash, Materials, etc. for construction costs incurred).

2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit Cash, Materials, etc. for construction costs incurred).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing A Complete Guide To Perform Internal And External Audits

Authors: Tim Power

1st Edition

1801490031, 978-1801490030

Students also viewed these Accounting questions