Required information (The following information applies to the questions displayed below.) Delph Company uses a job-order costing system and has two manufacturing departments- Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour Molding Fabrication Total 20,000 30,000 50,000 $ 700,000 $ 210,000 $ 910,000 $ 3.00 $ 1.00 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs-Job D-70 and Job C-200. It provided the following information related to those two jobs: Job D-70: Direct materials cost Direct labor cost Machine-hours Molding Fabrication Total $ 375,000 $325,000 $ 700,000 $ 200,000 $ 160,000 $360,000 14,000 6,000 20,000 Job C-200: Direct materials cost Direct labor cost Machine-hours Molding Fabrication Total $ 300,000 $ 250,000 $ 550,000 $ 175,000 $225,000 $ 400,000 6,000 24,000 30,000 Delph had no underapplied or overapplied manufacturing overhead during the year. 2. Assume Delph chooses to combine its departmental rates into a plantwide predetermined overhead rate based on machine-hours. a. Compute the plantwide predetermined overhead rate. b. Compute the total manufacturing cost assigned to Job D-70 and Job C-200. c. If Delph establishes bid prices that are 150% of total manufacturing costs, what bid prices would it have established for Job D-70 and Job C-200? d. What is Delph's cost of goods sold for the year? Complete this question by entering your answers in the tabs below. Required 2A Required 2B Required 2C Required 2D Assume Delph chooses to combine its departmental rates into a plantwide predetermined overhead rate based on machine- hours. Compute the plantwide predetermined overhead rate Predetermined overhead rate per MH Reguli 2 Required 2B >