Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Required information The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The companys cost analyst has concluded that utilities

Required information

The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The companys cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base that correlates with the cost. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst has decided to try both bases and has assembled the following information:

Quarter Tons Mined Direct Labor-Hours Utilities Cost
Year 1:
First 29,000 6,400 $ 64,000
Second 19,000 4,400 $ 59,000
Third 34,000 5,400 $ 74,000
Fourth 26,000 7,400 $ 89,000
Year 2:
First 32,000 12,800 $ 132,000
Second 39,000 13,200 $ 135,000
Third 44,000 10,800 $ 99,000
Fourth 42,000 13,800 $ 140,000

Required:

1-a. Using tons mined as the independent variable, prepare a scattergraph that plots tons mined on the horizontal axis and utilities cost on the vertical axis.

Instructions: 1. On the graph below, use the point tool (Year 1-1st quarter) to plot tons mined on the horizontal axis and utilities cost on the Vertical axis. 2. Repeat the same process for the plotter tools (Year 1-2nd quarter to Year 2-4th quarter). 3. To enter exact coordinates, click on the point and enter the values of x and y. 4. To remove a point from the graph, click on the point and select delete option.

1-b. Using the least-squares regression method, estimate the variable utilities cost per ton mined and the total fixed utilities cost per quarter. Express these estimates in the form Y = a + bX. (Round the Variable cost per unit to 2 decimal places and Fixed Cost to the nearest whole dollar amount.)

2-a. Using direct labor-hours as the independent variable, prepare a scattergraph that plots direct labor-hours on the horizontal axis and utilities cost on the vertical axis.

Instructions: 1. On the graph below, use the point tool (Year 1-1st quarter) to plot direct labor-hours on the horizontal axis and utilities cost on the Vertical axis. 2. Repeat the same process for the plotter tools (Year 1-2nd quarter to Year 2-4th quarter). 3. To enter exact coordinates, click on the point and enter the values of x and y. 4. To remove a point from the graph, click on the point and select delete option.

2-b. Using the least-squares regression method, estimate the variable utilities cost per direct labor-hour and the total fixed utilities cost per quarter. Express these estimates in the form Y = a + bX. (Round the Variable cost to 2 decimal places and Fixed Cost to the nearest whole dollar amount.)

3. Would you recommend that the company use tons mined or direct labor-hours as a base for planning utilities cost?

_Tons mined

_Direct labor-hours

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing Principles And Techniques

Authors: Richard L. Ratliff, W. Wallace, Walter B. Mcfarland, J. Loeboecke

2nd Edition

0894133268, 978-0894133268

More Books

Students also viewed these Accounting questions

Question

What would you do?

Answered: 1 week ago