Requlred Informatlon The following data is provided for a PPP project. To the People $105,000 per year beginning now $35,.000 per year To the Government
Requlred Informatlon The following data is provided for a PPP project. To the People $105,000 per year beginning now $35,.000 per year To the Government $1.8 million ndw and $200,000 every 3 years $70000 per year Benefits Cost Disbenefits Savings Calculate the modified benefit/cost ratios using an interest rate of 6% per year and an infinite project period. The modified B/C ratio is