Resource leveling: Resource leveling: makes use of float (slack) to move activities to to time slots other than the as early as possible dates. can
Resource leveling: Resource leveling: makes use of float (slack) to move activities to to time slots other than the "as early as possible" dates. can potentially turn non-critical activities into critical ones. makes the workload on resources more evenly distributed. all of these answers