Responding to Risk (PMBOK Guide Sixth Edition) Question 10 of 11 Question: What are some of the outputs of the Plan Risk Responses process? Instruction:
Responding to Risk (PMBOK Guide Sixth Edition) Question 10 of 11 Question: What are some of the outputs of the Plan Risk Responses process? Instruction: Choose all options that best answer the question. Answer Choices Disaster recovery plan updates Change requests Scope baseline updates Updates to the quality management plan Updates to the assumption log Procurement management plan updates Cost estimate updates