Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Reunion trip of 150 people. Based on the information below, an essay from the grading rubric description, I need help with this essay- Category Description

Reunion trip of 150 people.

Based on the information below, an essay from the grading rubric description, I need help with this essay-

CategoryDescriptionPoints%

General Business Presentation and Format

This should be a professional, well worded paper with a cver page that meets requirements and maintains continuity from start to finish. The paper uses proper references to important information, including items contained in the appendix. It uses appropriate citing and notation.

25

10

Executive Summary

This summarizes the content from the entire document with quantifiable highlights, such as overall project cost and schedule performance and estimate to completion, and makes the pitch to project stakeholders to continue the project. This is where you have to act as a project manager and a businessperson.

25

10

Schedule 1

This demonstrates proper use of Microsoft Project and the ability to correctly incorporate the provided data and establish a schedule with a baseline and review date at the planned 40% completion date.

25

10

Performance Analysis

This utilizes earned value data to analyze and provide proper interpretation of the project cost and schedule performance to date. It includes analysis of poorly performing tasks, critical path, and total project performance using earned value indicators, such as PV, EV, AC, CV, SV, CPI, and SPI.

50

20

EAC

This includes a forward-looking estimate of the project completion date and the final project costs based on the performance analysis.

50

20

Cost and Schedule Control Plan

This proposes appropriate corrective action(s) that should be taken at this point to put the project back on track based on the performance analysis.

25

10

Revised EAC

This includes the corrective actions from the control plan, along with the resulting cost impact and schedule impact. A cost versus benefit approach is used.

10

4

Schedule 2

This includes a revised MSP Gantt chart schedule (required) that reflects the impact of your corrective actions.

10

4

Appendix

This includes the required reports.

20

8

Lesson Learned

Discuss what you would do differently if you were going to take this project again.

10

4

Total

A quality paper will meet or exceed all of the above requirements.

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Start Plan activities for the family Planning Processes (3.2.2.1) Executi Closin Finish Sun 1/1/23 Tue 1/3/23 - Mon 1/9/23 Tue 1/10/23 - Fri 1/20/23 Mon Tue Tue 1/24/23 TIMELINE Reunion COMPLETE Initiation Payment Planning Phase COMPLETE Execution, Monitoring & Sun 1/1/23 COMPLETE Fri 1/20/23 Controlling COMPLETE Mon 1/9/23 Mon 1/23/23 EAC ACWP BCWP EARNED VALUE $30,600.00 $0.00 $0.00 Earned value management helps you quantify the performance of a project. It compares costs and schedules to a baseline to determine if the project is on track. If the charts don't look right, make sure you have set a baseline, EARNED VALUE OVER TIME assigned costs to tasks or resources, and entered progress. $1.00 The project's earned value based on the status date. If $0.90 actual cost (ACWP) is higher than earned value (BCWP), $0.80 then the project is over budget. If planned value (BCWS) EARNED VALUE REPORT is higher than earned value, then the project is behind $0.70 schedule. $0.60 $0.50 SO.40 Learn more about earned value $0.30 SO.20 $0.10 $0.00 '23 '23 '23GNATT CHART PT 1 Task Jan 1 2 Mode - Tack Narra " Curation - Start Finish S HT WTF SS M T W T FS Planning a destination family reunion for 150 people 17 days? Sun 1/1/28 Tun 1/24/2 Reunion COMPLETE 0 days Sun 1/1/23 Sun 1/1/23 Closing Processes 1 day? The 1/24/23 Tue 1/24523 Last day good byes [3.2 5 1] 1 day? Tue 1/24/8 Tue 1/24/28 43 Execution, Monitoring & Controlling COMPLETE 0 days Mon 1/23/2: Mon 1/28/28 40,41,42 Execution and Monitoring & Controlling Processes 1 day? Mon 1/23/2: Mon 1/23/25 Monitoring and Controlling Processes [3.2.4) 1 day? Mon 1/28/2: Mon 1/23/2: 38 Direct and Manage Project Execution (1.2.1.1) 1 day? Mon 1/29/2: Mon 1/23/2: 38 GANTT CHART INSERT STANDARD PRODUCT / SERVICE MOMT LIFE CYCLE 1 day? Mon 1/25/2! Man 1/23/21 38 Planning Phase COMPLETE Fri 1/20/23 Fri 1/20/23 Planning Procevies [32 2 1) The 1/10/25 Fri/20/2: Complete Schedule Development (3.3 39) 1 day Fri 1/20/23 Fri 1/20/23 25,26.27.13,16 Procurement Management Proceries The 1/17/23 Wed 1/18/2 Plan project contracting (1.2.1.21) 1 day Wed 1/18/2: Wed 1/18/21 35 Plan purchases and acquisitions (1.2.2.30] 1 day? Tue 1/17/23 Tue 1/17/23 30 A Risk Management Processes Tue 1/10/21 Mon JOB/2:Create Risk Response Planning Process (3.2.2.19) 1 day? Mon 1/16/23 Mon 1/16/23 30,31,32 Establish Quantitative Risk Analysis Process (3.2.2.18) 1 day? Wed 1/11/2: Wed 1/11/2: 29 Establish Qualitative Risk Analysis Process (3.2.2.17) 1 day? Wed 1/11/2: Wed 1/11/2: 29 Perform Initial Risk Identification (3.2.2.16) 1 day? Fri 1/13/23 Fri 1/13/23 29,17 Establish Risk Management Plan (3.2.2.15) 1 day? Tue 1/10/23 Tue 1/10/23 12 Complete Communication Plan (3.2.2.14) 4 days Fri 1/13/23 Wed 1/18/2: 17,12 Complete Quality Plan (3.2.2.12) 1 day? Tue 1/10/23 Tue 1/10/23 12 Cost Planning 2 days? Wed 1/18/2: Thu 1/19/23 GANTT CHART Develop cost budget (3.2.2.11) 1 day? Thu 1/19/23 Thu 1/19/23 24 Develop cost estimates (3.2.2.10) 1 day? Wed 1/18/2: Wed 1/18/2: 21,22 . Activity Planning 3 days? Fri 1/13/23 Tue 1/17/23 Define Activity Duration Estimates (3.2.2.8) 1 day? Tue 1/17/23 Tue 1/17/23 20 Define Activity Resource Estimates (3.2.2.7) 1 day? Tue 1/17/23 Tue 1/17/23 20 Determine Activity Sequence (3.2.2.6) 1 day? Mon 1/16/23 Mon 1/16/23 19 Define Activities (3.2.2.5) 1 day? Fri 1/13/23 Fri 1/13/23 17 Scope Management Processes 3 days? Tue 1/10/23 Thu 1/12/23 17 anta MA/DC to Inual of Work Darkanor /2 32 41 This 1/19/25 Thi. 1/19/29 16Create Risk Response Planning Process (3.2.2.19) 1 day? Mon 1/16/23 Mon 1/16/23 30,31,32 Establish Quantitative Risk Analysis Process (3.2.2.18) 1 day? Wed 1/11/2: Wed 1/11/2: 29 Establish Qualitative Risk Analysis Process (3.2.2.17) 1 day? Wed 1/11/2: Wed 1/11/2: 29 Perform Initial Risk Identification (3.2.2.16) 1 day? Fri 1/13/23 Fri 1/13/23 29,17 Establish Risk Management Plan (3.2.2.15) 1 day? Tue 1/10/23 Tue 1/10/23 12 Complete Communication Plan (3.2.2.14) 4 days Fri 1/13/23 Wed 1/18/2: 17,12 Complete Quality Plan (3.2.2.12) 1 day? Tue 1/10/23 Tue 1/10/23 12 Cost Planning 2 days? Wed 1/18/2: Thu 1/19/23 GANTT CHART Develop cost budget (3.2.2.11) 1 day? Thu 1/19/23 Thu 1/19/23 24 Develop cost estimates (3.2.2.10) 1 day? Wed 1/18/2: Wed 1/18/2: 21,22 Activity Planning 3 days? Fri 1/13/23 Tue 1/17/23 Define Activity Duration Estimates (3.2.2.8) 1 day? Tue 1/17/23 Tue 1/17/23 20 Define Activity Resource Estimates (3.2.2.7) 1 day? Tue 1/17/23 Tue 1/17/23 20 Determine Activity Sequence (3.2.2.6) 1 day? Mon 1/16/23 Mon 1/16/23 19 Define Activities (3.2.2.5) 1 day? Fri 1/13/23 Fri 1/13/23 17 14 4 Scope Management Processes 3 days? Tue 1/10/23 Thu 1/12/23 17 This 1/19/20 Thi 1/19/20 16Task Jan 1, '23 Jan 8, '23 i Mode Task Name Duration Start Finish Predecessors WTF S SMTWTFS SMTWTF S 14 Scope Management Processes 3 days? Tue 1/10/23 Thu 1/12/23 17 Create WBS to level of Work Packages (3.2.2.4) 1 day? Thu 1/12/23 Thu 1/12/23 16 16 Complete Scope Definition (3.2.2.3) 1 day? Wed 1/11/2: Wed 1/11/2: 15 un Perform Scope Planning (3.2.2.2) 1 day? Tue 1/10/23 Tue 1/10/23 12 Initiation Payment COMPLETE 0 days Mon 1/9/23 Mon 1/9/23 10,11 1/9 W Plan activities for the family 5 days? Tue 1/3/23 Mon 1/9/23 Find out costs for total trip 1 day? Mon 1/9/23 Mon 1/9/23 Collect Money to be received to 1 account 1 day Mon 1/9/23 Mon 1/9/23 8 GANTT CHART Develop a cost per family 1 day? Mon 1/9/23 Mon 1/9/23 8 Review all reservations 4 days Tue 1/3/23 Fri 1/6/23 Swimming and Dinner Day 1 day Fri 1/6/23 Fri 1/6/23 7 Hiking Day 1 day Thu 1/5/23 Thu 1/5/23 6 - NUOVO A Zoo Day 1 day Wed 1/4/23 Wed 1/4/23 5 Breakfast 1 day Tue 1/3/23 Tue 1/3/23 1,2 Plan a date and time 1 day Mon 1/2/23 Mon 1/2/23 Add all names of family members 1 day Mon 1/2/23 Mon 1/2/23Project Objectives The costs are Hotel Stay for ve days: $150 per family per day =$750 Zoo Visit total: $3600: $24 per ticket*150 people Hiking Day: FREE Swimming day FREE at the hotel Final Dinner together: $30 per plate = $4500. Dinner accommodations Schedule and quality objectives are a day to go to the zoo, a day to hike, a swimming day, and then a nal dinner day for us all s to be acceptable to the customer when the complete day. The other two days are free falls for what you would like to do downtown Atlanta for those days with whomever. It gives us time to do some things together to bond and catch up for the year

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods For Managers

Authors: John Gill, Phil Johnson

4th Edition

1847870945, 9781847870940

More Books

Students also viewed these General Management questions

Question

What do you see as your biggest strength/weakness?

Answered: 1 week ago