Question
Revenue Recognition Franken Stein Company began construction on a new scientific laboratory in 2016.The contract price is $6,500,000 and the lab will be completed mid-2018.The
Revenue Recognition
Franken Stein Company began construction on a new scientific laboratory in 2016.The contract price is $6,500,000 and the lab will be completed mid-2018.The following is a year-by-year recap of construction costs incurred and the estimated costs to complete the project as of the end of each year.Progress billings and cash collections are also indicated.
201620172018
Actual costs incurred during the year$1,600,000$2,250,000$1,800,000
Estimated costs to complete3,550,0001,650,000-0-
Billings made during the year1,400,0003,200,0001,900,000
Cash collections during the year1,000,0002,650,0002,850,000
Instructions:
1.Determine the amount of revenue to be recognized in each of the three years applying the long-term contract method. (round to nearest whole percent)
2.Prepare the necessary journal entries for each of the three years to account for construction costs incurred, recognized revenue and cost of construction, contract billings, and cash collections.
3.Prepare the necessary journal entry to close the construction accounts in 2018.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started