Activity | Predecessor | Duration in Hours |
A | None | 40 |
B | None | 25 |
C | A | 35 |
D | B,C | 30 |
E | C | 10 |
F | D,E | 22 |
:
What is the minimum duration for this project?
What activities are on the critical path?