Reynolds Manufacturers Inc. has estimated total factory overhead costs of $133,100 and expected direct labor hours of 12,100 for the current fiscal year. If Job
Reynolds Manufacturers Inc. has estimated total factory overhead costs of $133,100 and expected direct labor hours of 12,100 for the current fiscal year. If Job 117 incurs 1,140 direct labor hours, Work in Process will be debited and Factory Overhead will be credited for Oa. S1,140 Ob. 966,550 Oc. $133,100 Od. $12,540