Reynolds Manufacturers Inc. has estimated total factory overhead costs of $95,000 and expected direct labor hours of 9,500 for the current fiscal year. If job
Reynolds Manufacturers Inc. has estimated total factory overhead costs of $95,000 and expected direct labor hours of 9,500 for the current fiscal year. If job number 117 incurred 2,300 direct labor hours, Work in Process will be debited and Factory Overhead will be credited for $2,300 $21,850 $23,000 $95,000