Rick Wing has a repetitive manufacturing plant that produces automobile steering wheels. The firm uses a work year of 2 9 0 days. After several

Rick Wing has a repetitive manufacturing plant that produces automobile steering wheels. The firm uses a work year of 290 days. After several hours of analysis, suppose you developed the following data for steering wheels.
Annual demand for steering wheels 29,000
Daily demand 100
Daily production (8 hours)1,040
Desired lot size (2 hours of production)260
Holding cost per unit per year 2.5
What is the setup time in minutes, based on $60 per hour setup labour?
(please answer to two decimal places, e.g.,10.01)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Becoming A Top Manager Tools And Lessons In Transitioning To General Management

Authors: Kevin Kaiser, Michael Pich, I. J. Schecter

1st Edition

1118858573, 978-1118858578

More Books

Students also viewed these General Management questions

Question

What internal and external forces were influencing DigiTech?

Answered: 1 week ago