Rider Manufacturing has gathered the following information for the past week of performance:
Actual hours worked: 18,500
Standard hours allowed: 20,000
Total direct labour variance: $8,300 F
Direct labour price variance: $3,700 U
Direct labour efficiency variance: $12,000 F
The standard direct labour price per hour was: