right. Please report to me with the facts, issues and your recommendations related to the last bid package prepared by GCI. John Mitchell, CPC President,
right". Please report to me with the facts,
issues and your recommendations related to
the last bid package prepared by GCI.
John Mitchell, CPC
President, GCI
About fifteen minutes before bid time, the manager of estimating
determined that GCI was the only bidder on the job and instructed
the junior estimator to increase the total bid including regular
overhead and profit by which is still within the owner's
budget price.