Riverbed Manufacturing spends 55 minutes per order on non-value-added activities. The total manufacturing cycle time is 1.3 hours. Calculate the manufacturing cycle efficiency. (Round answer

Riverbed Manufacturing spends 55 minutes per order on non-value-added activities. The total manufacturing cycle time is 1.3 hours.

Calculate the manufacturing cycle efficiency. (Round answer to 1 decimal place, e.g. 5.1%.)

My answer: 1.3 hours equals 78 minutes

78-55=23

23/78=0.29

Tried the following answers and none are correct: 2.9, 3.0, 0.29, 0.30

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Robert Kemp, Jeffrey Waybright

4th edition

978-0134125053, 9780134114781, 134125053, 134114787, 978-0134436111

More Books

Students also viewed these Accounting questions

Question

sun000 5>0000 535000

Answered: 1 week ago

Question

3. What is my goal?

Answered: 1 week ago

Question

2. I try to be as logical as possible

Answered: 1 week ago