Question
Rocky Mountain Corporation makes two types of hiking bootsXactive and Pathbreaker. Data concerning these two product lines appear below: Xactive Pathbreaker Direct materials per unit
Rocky Mountain Corporation makes two types of hiking bootsXactive and Pathbreaker. Data concerning these two product lines appear below: |
Xactive | Pathbreaker | |||||
Direct materials per unit | $ | 63.90 | $ | 50.10 | ||
Direct labor cost per unit | $ | 17.30 | $ | 12.10 | ||
Direct labor-hours per unit | 1.4 | DLHs | 1 | DLHs | ||
Estimated annual production and sales | 16,000 | units | 66,000 | units | ||
|
The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for the upcoming year appear below: |
Estimated total manufacturing overhead | $1,688,440 | |
Estimated total direct labor-hours | 88,400 | DLHs |
|
Required: |
1-a. | Compute the predetermined overhead rate based on direct labor-hours. (Round the intermediate calculations and final answer to two decimal places.) | |
1-b. | Using the predetermined overhead rate and other data from the problem, determine the unit product cost of each product. (Round the intermediate calculations and final answer to two decimal places.) | |
2. | The company is considering replacing its conventional costing system with an activity-based costing system that would assign its manufacturing overhead to the following four activity cost pools: |
Estimated Overhead Cost | Expected Activity | ||||
|
|
| |||
Activity Cost Pools and Activity Measures | Xactive | Pathbreaker | Total | ||
Supporting direct labor (direct labor-hours) | $ | 601,120 | 22,400 | 66,000 | 88,400 |
Batch setups (setups) | 387,500 | 205 | 105 | 310 | |
Product sustaining (number of products) | 644,060 | 1 | 1 | 2 | |
General factory (machine-hours) | 55,760 | 1,600 | 6,600 | 8,200 | |
|
| ||||
Total manufacturing overhead cost | $ | 1,688,440 | |||
|
| ||||
|
Determine the activity rate for each of the four activity cost pools. (Round your final answers to 2 decimal places.) | |
3. | Using the activity rates and other data from the problem, determine the unit product cost of each product. (Round the intermediate calculations and final answer to two decimal places.) |
Figure out 3 please. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started