Rogers Ltd. has entered into a contract beginning in February 2020 to build two warehouses for ocean Ltd. The contract is a non-cancellable fixed price
Rogers Ltd. has entered into a contract beginning in February 2020 to build two warehouses for ocean Ltd. The contract is a non-cancellable fixed price contract for $9.4 million. The following data pertain to the construction period.
2020 | 2021 | 2022 | ||||
Costs for the year | $3,285,000 | 4,015,000 | 1,800,000 | |||
Estimated costs to complete | 4,015,000 | 1,825,000 | -0- | |||
Progress billings for the year (non-refundable) | 2,960,000 | 3,440,000 | 3,000,000 | |||
Cash collected for the year | 2,605,000 | 3,490,000 | 3,305,000 |
a) Using the percentage-of-completion method, calculate the percent complete for each year of the contract.
b) Calculate the amount of the gross profit to be recognized each year of the contract.
c) Prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.)
d) What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021? Show how the construction contract would be reported on the SFP and the income statement for the year ended December 31, 2021
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started