Roman Manufacturings July production involved actual direct labor cost of 63,497 for 4,700 direct labor hours. The budget for the July level of production called

Roman Manufacturings July production involved actual direct labor cost of 63,497 for 4,700 direct labor hours. The budget for the July level of production called for 4,800 direct labor hours at 13.50 per hour, using a standard cost system.

What is Romans labor efficiency variance for July?

a) 1,303 favorable

b) 1,350 favorable

c) 47 unfavorable

d) 1,303 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Accounting

Authors: Needles, Powers, crosson

11th Edition

1439037744, 978-1133626985, 978-1439037744

More Books

Students also viewed these Accounting questions

Question

for the value of 0.597, the floor value is

Answered: 1 week ago