Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7 , Ron is reviewing
Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day Ron is reviewing the Gantt chart depicting these schedules:
Job # was scheduled to begin on day and to take days. It got started on time and is day ahead of schedule.
Job # was scheduled to begin on day and take days. It is currently on time.
Job # was scheduled to start on day and take days. It actually got started on day and is progressing according to plan.
Job # was scheduled to begin on day but missing equipment delayed it until day It is progressing as expected and should take days.
Job # was scheduled to begin on day and take days. It got started on time but has since fallen behind
This exercise contains only part a
Part
a Add the actual progress to the Gantt schedule shown on the righton which the planned timings have been already plotted as blue lines
Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top ofoverlapping the maroon dashed line provided just above the job number for each of the tasks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started