Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks)

 

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Predecessor(s) Activity Activity A B C D E F a Time (weeks) 6 1 8 5 1 5 m 9 9 12 7 3 8 b 10 24 16 9 4 20 A A A B C, E G H 1 J K a) The expected (estimated) time for activity C is 12 weeks. (Round your response to two decimal places.) b) The variance for activity C is weeks. (Round your response to two decimal places.) a 2 1 7 6 1 m 3 1 7 8 1 b 5 1 7 12 4 Immediate Predecessor(s) C, E F F D, G, H 1, J

Step by Step Solution

3.46 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

Answer Activity A BCDEFG ta tm Weeks Weeks 6 9 G H I J K Answer tb Weeks 10 23 16 10 4 21 4 1 7 1... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability and Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson

12th edition

978-0134163512, 134163516, 134130421, 978-0134130422

More Books

Students also viewed these General Management questions

Question

How do you define each of these functions?

Answered: 1 week ago