Rudd Clothiers is a small company that manufactures tall-mens suits. The company has used a standard cost accounting system. In May 2017, 10,400 suits were

Rudd Clothiers is a small company that manufactures tall-mens suits. The company has used a standard cost accounting system. In May 2017, 10,400 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,000 direct labor hours. All materials purchased were used.

Cost Element

Standard (per unit)

Actual

Direct materials 6 yards at $4.50 per yard $276,760 for 62,900 yards ($4.40 per yard)
Direct labor 1.41 hours at $13.80 per hour $219,589 for 15,464 hours ($14.20 per hour)
Overhead 1.41 hours at $7.30 per hour (fixed $4.90; variable $2.40) $48,800 fixed overhead $36,500 variable overhead

Overhead is applied on the basis of direct labor hours. At normal capacity, budgeted fixed overhead costs were $68,600, and budgeted variable overhead was $33,600. Compute the overhead controllable variance and the overhead volume variance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Finance Text And Cases

Authors: Vishwanath S. R.

3rd Edition

9353282896, 978-9353282899

More Books

Students also viewed these Accounting questions

Question

x-3+1, x23 Let f(x) = -*+3, * Answered: 1 week ago

Answered: 1 week ago

Question

What is the major competition for your organization?

Answered: 1 week ago

Question

How accurate is this existing information?

Answered: 1 week ago