Saffer Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Show all work wait time...........21.6 hrs
Saffer Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Show all work wait time...........21.6 hrs process time...........1.6 hrs inspection time..............0.2 hrs move time............3.1 hrs queue time.........4.4 hrs The throughput time is: The manufacturing cycle efficiency (MCE) is: The delivery cycle time is