Sally is the project manager of a new payroll implementation project. Her team has provided her with : document that lists all of the risks
Sally is the project manager of a new payroll implementation project. Her team has provided her with : document that lists all of the risks by category in a hierarchical fashion. What is this document called? List of identified risks Risk register Risk breakdown structure Risk management plan