Samson Construction has the following work on hand: Job Contract Price Gross Profit Amount Billed Percent Complete 1 $ 800,000 $ 80,000 $600,000 50% 2
Samson Construction has the following work on hand: Job Contract Price Gross Profit Amount Billed Percent Complete 1 $ 800,000 $ 80,000 $600,000 50% 2 $2,000,000 $200,000 $350,000 10% On a cost basis, Samson's backlog is Available answer options Select only one option A $960,000. B $1,850,000. C $1,980,000. D $2,800,000