Santiago Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture

Santiago Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows:

Line Item Description Standard Costs Actual Costs
Direct materials 182,000 lbs. at $5.80 per lb. 180,200 lbs. at $5.60 per lb.
Direct labor 17,500 hrs. at $17.80 per hr. 17,900 hrs. at $18.00 per hr.
Factory overhead Rates per direct labor hr., based on 100% of normal capacity of 18,260 direct labor hrs.:
Factory overhead Variable cost, $3.90 $67,570 variable cost
Factory overhead Fixed cost, $6.20 $113,212 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Line Item Description Amount Variance
Direct Materials Price Variance $fill in the blank FavorableUnfavorableFavorable
Direct Materials Quantity Variance $fill in the blank FavorableUnfavorableFavorable
Total Direct Materials Cost Variance $fill in the blank FavorableUnfavorableFavorable

b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Line Item Description Amount Variance
Direct Labor Rate Variance $fill in the blank FavorableUnfavorableUnfavorable
Direct Labor Time Variance $fill in the blank FavorableUnfavorableUnfavorable
Total Direct Labor Cost Variance $fill in the blank FavorableUnfavorableUnfavorable

c. Determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Line Item Description Amount Variance
Variable factory overhead controllable variance $fill in the blank FavorableUnfavorableFavorable
Fixed factory overhead volume variance $fill in the blank FavorableUnfavorableUnfavorable
Total factory overhead cost variance $fill in the blank FavorableUnfavorableUnfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Activity Based Cost Management In Government

Authors: Gary Cokins

2nd Edition

1567261817, 978-1567261813

More Books

Students also viewed these Accounting questions

Question

16.8 Explain the typical steps in a grievance procedure.

Answered: 1 week ago

Question

16.4 Outline the five steps in the labour relations process.

Answered: 1 week ago