Sara is the project manager for a large conference. The project's budget is $ 6 0 , 0 0 0 , and the project is
Sara is the project manager for a large conference. The project's budget is $ and the project is scheduled for six months. By working hard and smart, Sara and the team were able to complete the project in three months and spent only $ Now with the project completed, what is the VAC of the project?