Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most

Sara is using three point estimation technique to estimate time required to complete a task. The best case scenario estimation is: 11 weeks, the most likely estimation is 14 weeks, and the estimation that considers all the risks is 17 weeks.

Calculate the time estimation for Saras task. Use PERT for your calculation. (5 marks)

(4 marks for working, 1 mark for time estimate)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting

Authors: Srivastava Lal, Jawahar Lal

5th Edition

1259026523, 978-1259026522

More Books

Students also viewed these Accounting questions

Question

Cite common obstacles to reaching your goals.

Answered: 1 week ago