Question
1 Approved Answer
Savg Help Sava A job was budgeted to require 8 hours of labor per unit at $9.00 p job consisted of 8,600 units and
Savg Help Sava A job was budgeted to require 8 hours of labor per unit at $9.00 p job consisted of 8,600 units and was compieted in 65,800 hours total labor cost of $624,200. What is the direct labor efficiency varian $12000 unfavorable $22000 orable $27005 unfavorable 0 $27000 ferrade $5000 interrable.