Scenario 2: A network consists of the following list. Times are given in weeks. (Keep two decimal place in your calculation) Activity Preceding Optimistic Probable
- Scenario 2: A network consists of the following list. Times are given in weeks. (Keep two decimal place in your calculation)
Activity | Preceding | Optimistic | Probable | Pessimistic | Expected Time | Variance |
A | -- | 5 | 11 | 14 | ||
B | - | 3 | 3 | 9 | 4.00 | 1.00 |
C | -- | 6 | 10 | 14 | 10.00 | 1.78 |
D | A, B | 3 | 5 | 7 | 5.00 | 0.44 |
E | B | 4 | 6 | 11 | 6.50 | 1.36 |
F | C | 6 | 8 | 13 | 8.50 | 1.36 |
G | D, E | 2 | 4 | 6 | 4.00 | 0.44 |
H | F | 3 | 3 | 9 | 4.00 | 1.00 |
(3 points) a. Calculate the expected duration and variance of activity A (Keep two decimal place in your calculation & show your calculation steps). (3 points) b. Calculate the duration of the placescritical path. (3 points) c. Calculate the project variance and project standard deviation (Keep two decimal place in your calculation & show your calculation steps). (6 points) d. Calculate the probability that the project will be completed in more than 28 weeks (Keep two decimal place in your calculation, e.g. X.XX% & show your calculation steps).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started