Scenario 2. You are the contracting officer for contract W0054219P0052 for the delivery of five rail carts. One month after award, you receive notice from
Scenario 2. You are the contracting officer for contract W0054219P0052 for the delivery of five rail carts. One month after award, you receive notice from the requiring activity that the rail cars need to be delivered to El Paso, TX instead of San Antonio, TX. There will be no change to the required delivery date.
- Is this proposed change within the general scope of the current contract?(citation not required)
2. How could you execute the requiring activity's request for a change?
3 . Ifthis change will be accomplished through a modification to the current contract, will the modification be executed as a unilateral or a bilateral modification?
4.What is the authority for the modification?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started