Scenario 2. You are the contracting officer for contract W0054219P0052 for the delivery of five rail carts. One month after award, you receive notice from

Scenario 2. You are the contracting officer for contract W0054219P0052 for the delivery of five rail carts. One month after award, you receive notice from the requiring activity that the rail cars need to be delivered to El Paso, TX instead of San Antonio, TX. There will be no change to the required delivery date.

  1. Is this proposed change within the general scope of the current contract?(citation not required)

2. How could you execute the requiring activity's request for a change?

3 . Ifthis change will be accomplished through a modification to the current contract, will the modification be executed as a unilateral or a bilateral modification?

4.What is the authority for the modification?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Aviation Marketing And Management

Authors: Alexander T. Wells, Bruce D. Chadbourne

2nd Edition

1575241927, 978-1575241920

More Books

Students also viewed these General Management questions

Question

Sketch the following sets of points. {(r, 0): 2 r 8}

Answered: 1 week ago

Question

What is the meaning and definition of E-Business?

Answered: 1 week ago

Question

Define indirect financial compensation (employee benefits).

Answered: 1 week ago

Question

Describe the selection decision.

Answered: 1 week ago