Scenario Steels R Ours (SRO) is a manufacturer and supplier of steels in Suva. General Contractors Ltd (GCL) agreed to purchase 50 tonnes of steel
Scenario
Steels R Ours (SRO) is a manufacturer and supplier of steels in Suva. General Contractors Ltd (GCL) agreed to purchase 50 tonnes of steel from Steels R Ours. The price was fixed at $5,000 per tonne. The delivery was to be made 2 weeks after the signing of the agreement. The agreement was signed on 01 March 2021. The price was to be paid one month after the delivery of the steel to General Contractors Ltd's yard in Manoca, Nausori. To ensure that the steel complies with the National Building Code 2020 (NBC); non-destructive tests such as bending, di-penetration, magnetic particles are carried out to find the strength of the steel structure. The agreement explicitly states that the steel must comply with the National Building Code 2020. As agreed, Steels R Ours delivered 50 tonnes of steel to General Contractors Ltd's yard in Manoca, Nausori. However, on examination, it was discovered that only 35 tonnes of steel meet the requirements of the National Building Code 2020 (NBC). General Contractors Ltd sold 40 tonnes of steel to Easybuild but had to recall the steels because it did not meet the requirements of the NBC 2020. (a) Advise General Contractors Ltd (GCL); and
(b) How would your answer differ from (a) if Steels R Ours was unable to conduct the strength test due to unforeseen circumstances and as such only supplied 15 tonnes of steel?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started