Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Scenario You have been hired as a project manager for a software company, ABC Solutions. Their business development team has received a product request from

Scenario

You have been hired as a project manager for a software company, ABC Solutions. Their business development team has received a product request from a new client, XYZ Financial Services. They need a custom software solution to streamline some workflows and processes that will be implemented in their offices worldwide. Your company has developed a similar software solution, but the client requires additional features and customization. The new software needs to be ready for a test run at two of the offices in about six months and worldwide rollout in another three months. Your boss, the project director, has asked you to manage this product development project.

ABC Solutions uses the traditional waterfall method for software development. The proposed project schedule should include the following major tasks:

  • Determine the software requirements and design.
  • Conduct a code test and system test.
  • Address issues with the software.
  • Deliver the prototype.

You have been asked to assemble a team with the skills and expertise to perform these tasks.

Before initiating the project, you, the project director, and a software architect meet with the IT director and product manager of XYZ Financial Services to understand their requirements. They explain that the custom software should include three new features, five feature customizations, and a new interface design to match the client's brand colors and logo.

Later, you and some key team members analyze the scope and requirements to arrive at some critical decisions and conclusions. These have been summarized in two project documents:

  • The XYZ Business Workflow Project Charter that includes the project objectives and other important details
  • A document with the XYZ Business Workflow Resource and Effort Estimates for each development task

You will need to choose and allocate resources from the following available team members: a user interface (UI) designer, UI developers, a software architect, technical team leads, software developers, and software testers. You will also have access to two team members from the development team of the original software who will act as consultants for your team. However, these members are only available part time since they are also busy on other projects.

Directions

Specifically, you must address the following rubric criteria:

Project Planning

  1. Use the information from the scenario, including the project charter and effort estimates, to generate a single file that includes the following components: stakeholder register, risk register, work breakdown structure (WBS), and responsibility matrix. You can also make reasonable assumptions to help you complete these tasks, but be sure to explain your assumptions. Address each of the tasks outlined below.
  2. Stakeholder register: Identify and list the stakeholders for this project. Ensure it includes the following details:
    1. Their names
    2. Their role in the project
    3. Their influence on the project and its outcomes
  3. Risk register: Identify and describe at least four individual project risks, including the risks identified in the project charter. The register should include the following details for each risk:
    1. The description of the risk
    2. The probability the risk may occur
    3. The impact the risk can have on the project
    4. The response plan if the risk occurs
    5. The person responsible for handling the risk
    6. The status of the risk
  4. Work Breakdown Structure (WBS) and Networking Diagram: Include the major milestones. Tasks are arranged sequentially; indicate dependencies between tasks.
    1. generate a WBS for the project, dividing project deliverables into manageable tasks.
    2. generate a networking diagram that organizes the project tasks chronologically.
    3. Indicate any dependencies between tasks.
  5. Responsibility Assignment Matrix: generate a responsibility matrix with a responsible, accountable, consulted, and informed (RACI) chart that shows how the tasks in the project are assigned to the respective team members. Also, include a RACI chart for all stakeholders you identified earlier.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Strategic Managerial Approach

Authors: Jack R. Meredith, Scott M. Shafer, Samuel J. Mantel Jr.

11th Edition

1119803837, 978-1119803836

More Books

Students also viewed these General Management questions

Question

Job type Retail sales, managerial, human resources, etc.

Answered: 1 week ago

Question

What types of questions would make up a behavioral interview?

Answered: 1 week ago