Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 2 C A 5 D B 6 E C%media:cm.png% D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 2
C A 5
D B 6
E C%media:cm.png% D 2
F D 3
G F 5
H E%media:cm.png% G 4

What is the critical path?

  1. multiple choice 1

A-C-E-F-G-H

A-C-E-H

A-C-E-G-H

A-B-D-F-G-H

How many weeks will it take to complete the project?

Which activities have slack, and how much?

  1. multiple choice 2

E 1 week H 4 weeks.

C 9 weeks E 6 weeks.

B 1 week D 3 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Optimization In Operations Research

Authors: Ronald L. Rardin

1st Edition

0023984155, 9780023984150

More Books

Students also viewed these General Management questions