Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 2 E C D
Schedule the following activities using CPM: |
ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
A |
| 3 |
B | A | 5 |
C | A | 4 |
D | B | 2 |
E | C D | 3 |
F | D | 1 |
G | F | 1 |
H | E G | 4 |
b. | What is the critical path? | ||||||||
|
| ||||||||
|
|
c. | How many weeks will it take to complete the project? |
Number of weeks |
|
d. | Which activities have slack, and how much? | ||||||
|
| ||||||
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started