Question

1 Approved Answer

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 5 C A 4 D B 2 E C D

Schedule the following activities using CPM:

ACTIVITY

IMMEDIATE PREDECESSOR

TIME (WEEKS)

A

3

B

A

5

C

A

4

D

B

2

E

C D

3

F

D

1

G

F

1

H

E G

4

b.

What is the critical path?

A-C-E-H

A-C-E-F-G-H

A-B-D-F-G-H

A-B-D-E-H

c.

How many weeks will it take to complete the project?

Number of weeks

d.

Which activities have slack, and how much?

C 3 weeks F 1 week G 1 week.

B 3 weeks D 2 weeks E 4 weeks.

A 1 week B 2 weeks D 4 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

A First Course in Quantitative Finance

Authors: Thomas Mazzoni

1st edition

9781108411431, 978-1108419574

More Books

Students also viewed these Finance questions