Schedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A 1 B A 4 C A 3 D B 2 E C, D
Schedule the following activities using CPM:
Activity
Immediate Predecessor
Time (weeks)
A
1
B
A
4
C
A
3
D
B
2
E
C, D
5
F
D
2
G
F
2
H
E, G
3
Draw the network.
What is the critical path?
page 101
How many weeks will it take to complete the project?
Which activities have slack, and how much?