Schedule the following activities using CPM: table [ [ Activity , Immediate Predecessor,Time ( weeks ) ] , [ A , - , 1
Schedule the following activities using CPM:
tableActivityImmediate Predecessor,Time weeksABACADBEC DFDGFHE G
a Draw the network.
b What is the critical path?
c How many weeks will it take to complete the project?
d Which activities have slack, and how much?