Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , 5

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,5],[B,A,3],[C,A,4],[D,B,6],[E,C%media:cm.png% D,8],[F,D,2],[G,F,4],[H,E%media:cm.png% G,3]]
b. What is the critical path?
A-B-D-E-H
A-B-D-F-G-H
A-C-E-H
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
B,1 week; H,2 weeks; F,4 weeks.
C,5 weeks; F,2 weeks; G,2 weeks.
A,2 weeks; C,3 weeks; F,1 week.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Society Research On Audit Practice And Regulations

Authors: Wally Smieliauskas, Minlei Ye, Ping Zhang

1st Edition

1138314129, 978-1138314122

More Books

Students also viewed these Accounting questions

Question

Define and describe the sections in a job description.

Answered: 1 week ago

Question

Discuss the relationship between job analysis and HRM processes.

Answered: 1 week ago