Scheem Company manufactures a variety of prestige boardroom chairs. Its job-costing system uses an activity-based approach. There are two direct-cost categories (direct materials and direct
Scheem Company manufactures a variety of prestige boardroom chairs. Its job-costing system uses an activity-based approach. There are two direct-cost categories (direct materials and direct manufacturing labour) and three indirect-cost pools. The cost pools represent three activity areas at the plant.
Manufacturing Activity Area | Budgeted Costs for 2019 | Cost Driver used as Allocation base | Cost-allocation rate |
Materials handling | R200 000 | Parts | R0.25 |
Cutting | R2 000 000 | Parts | R2.50 |
Assembly | R2 000 000 | Direct manufacturing labour hours | R25.00 |
Two styles of chairs were produced in March: the executive chair and the chairman chair. Their quantities, direct materials costs, and other data for May 2019 are as follows:
| Units produced | Direct material costs | Number of parts | Direct manufacturing labour hours |
Executive chair | 5 000 | R600 000 | 100 000 | 7 500 |
Chairman chair | 100 | R25 000 | 3 500 | 500 |
The direct manufacturing labour rate is R20 per hour. Assume no beginning or ending inventory.
Required:
2.1 Calculate the May 2019 total manufacturing costs and unit costs of the executive chair and the chairman chair.
2.2 The upstream activities to manufacturing (R&D and design) and the downstream activities (marketing, distribution, and customer service) are analyzed, and the unit costs in 2019 are budgeted to be:
Upstream Activities | Downstream Activities | |
Executive chair | R60 | R110 |
Chairman chair | R146 | R236 |
Calculate the full cost per unit of each chair. (Full costs of each chair is the sum of the costs of all business functions in the value chain.)
2.3 Compare the per-unit costs figures for the executive chair and the chairman chair calculated in 2.1 and 2.2 above. Why do these costs differ for each chair? Why might these differences be important to Scheem Company?
Step by Step Solution
3.45 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
1 Using the Activity based costing calculate first the overhead costs in each products Executive Cha...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started