The following table shows the activities for a small project. Allowing activities to be interrupted determine for each activity its early and late dates.

 

The following table shows the activities for a small project. Allowing activities to be interrupted determine for each activity its early and late dates. Determine the critical path and calculate the total float of all activities What is the effect on total project duration if activity H duration was extended by 3 days Activity A B C D E F G H I J K L Duration (days) 2 7 6 3 3 7 8 3 2 5 3 4 Dependence Relationships A A A B B, C D E,F F I F, G H K FF FS FS FS FS FS FS FS SS FS SS FS Lag 5 2 -1 - 3 5

Step by Step Solution

3.29 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

ANSWER We calculate the early and late dates by defining the following definitions a Early Start ES It is the earliest possible start time for an acti... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistics The Art And Science Of Learning From Data

Authors: Alan Agresti, Christine A. Franklin

3rd Edition

9780321849281, 321755944, 321849280, 978-0321755940

More Books

Students also viewed these Finance questions

Question

What is the test for whether a hypothesis is scientific or not?

Answered: 1 week ago

Question

5t-6, x 4 Given f(x)=x

Answered: 1 week ago

Question

=+b. Calculate the reliability at t 5 800,000 cycles.

Answered: 1 week ago

Question

=+b. Examine the chart in part (a) for any out-ofcontrol points.

Answered: 1 week ago