Question

1 Approved Answer

Scope Management Plan Purpose: The purpose of this scope management plan is to ensure that the project team understands and agrees upon the project's objectives,

Scope Management Plan

  1. Purpose: The purpose of this scope management plan is to ensure that the project team understands and agrees upon the project's objectives, deliverables, and boundaries, and that the project's scope is controlled throughout its lifecycle to meet these objectives and deliverables.

  1. The project scope includes two main components:
  • Warehouse remodeling and Reconstruction
  • Inventory Barcode System Implementation

The project objectives are to remodel and reconstruct the warehouse in a way that is easy for the logistics team to conduct inventory influx and outflow and to implement an inventory barcode system that keeps a track of the inventory for easy tracking and reduced shrinkage.

  1. Scope Management Approach

The scope management approach will be guided by the following principles:

  • Clear communication and documentation of the project objectives, deliverables, and boundaries
  • Ongoing stakeholder engagement and collaboration to ensure alignment with project goals and scope
  • Robust change management processes to evaluate and approve any scope changes
  • Regular monitoring and reporting of project progress against the scope baseline

4. Scope Change Management:

Scope changes will be evaluated and approved through the following process:

  • Identification and documentation of the proposed scope change, including its impact on project objectives, deliverables, and boundaries
  • Evaluation of the proposed scope change by the project team and stakeholders to determine its feasibility and alignment with project goals
  • Approval or rejection of the proposed scope change by the project sponsor or steering committee
  • Documentation of the approved scope change and its impact on the project's cost, schedule, and quality constraints

Question:- 1)Please help me to make change management plan for the above mentioned topic. it would be better if you provide the plan in table format (Table format)

2)Need detailed Resource management plan outlining of human and non human resources, ensuring their availability and efficient utilization throughout the project (table format)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Anger Management Workbook For Moms

Authors: Lena Suarez Angelino

1st Edition

1638074755, 978-1638074755

More Books

Students also viewed these General Management questions