Scorpio Company's activity for the first five months of 2006 are as follows: Machine Hours Electrical Cost January 2,100 $2,400 February 2,700 $3,300 March 2,600
Scorpio Company's activity for the first five months of 2006 are as follows: | |||
Machine Hours | Electrical Cost | ||
January | 2,100 | $2,400 | |
February | 2,700 | $3,300 | |
March | 2,600 | $2,900 | |
April | 2,900 | $3,200 | |
May | 2,400 | $2,600 | |
___ 25. | Using the high-low method, how much is the cost per machine hour? |