Question
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2021.
At December 31, 2022, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18,000,000 due to unanticipated price increases. What is reported in the balance sheet at December 31, 2022 for Seasons as the difference between the Construction in Process and the Billings on Construction in Process accounts, and is it a debit or a credit?
Difference between the accounts Debit/Credit
a. $4,225,000 Credit
b. $1,550,000 Debit
c. $1,100,000 Debit
d. $1,550,000 Credit
ANSWER: b (Need explanation)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started