Section 2: To identify the right set of suppliers to supply the materials to the proposed inventory backup location Section 1: The distance from the

Section 2: To identify the right set of suppliers to supply the materials to the proposed inventory backup location

Section 1:

  • The distance from the existing Inventory locations in Lucknow, Noida, and Kolkata to the proposed backup inventory location must be more than 2600 kms
  • Minimize the cost
  • The available datasets include:
    • The distance in kilometers between the existing Inventory locations and the proposed Backup locations.
    • The transportation and holding costs between the existing Inventory locations and the proposed Backup locations.
    • The quantity to be transported from the proposed Backup location to the existing Inventory locations.
    • The cost components associated with the Backup inventory locations.

You need to find answers to the following questions:

1. Find out the optimum backup inventory location

2. Optimal Cost

Existing Inventory Locations vs Proposed Back up locations Transportation & Holding Cost

Holding / Transportation Cost Lucknow Noida Kolkata
Kochi 4 4 8
Coimbatore 6 6 5
Mysore 8 6 5

Quantity to be handled from proposed back up location to existing inventory location

Qty Lucknow Noida Kolkata
Buffer Inv 5000 3000 3000
Buffer Inv 2300 2700 2600
Buffer Inv 1900 2500 2400
Demand 9200 8200 8000

Cost elements for the back up locations

Buffer Inventory Capacity Building Cost
Kochi 35000 1100000
Coimbatore 31000 1700000
Mysore 32000 1500000

After deciding on where to build the buffer inventory, suggest the optimum list of suppliers that we need to place the order to send to the Buffer Inventory

The given data:

- List of suppliers -Maximum capacity

- Transportation cost

The quantity to be supplied from identified suppliers to the proposed backup location

To find:

1 . Decision to which suppliers the orders should be placed

2. Optimal Cost

Proposed backup location Vs List of suppliers -Transportation and holding cost

Transportation Cost S1 S2 S3 S4 S5
Kochi 2 3 9 5 4
Coimbatore 3 5 4 3 1
Mysore 3 3 4 2 3

List of suppliers max capacity

Supplier Capacity to Ship
S1 5000
S2 8000
S3 7000
S4 9000
S5 6000

The Quantity to be supplied from suppliers to the proposed back up location

Qty Lucknow Noida Kolkata
Demand 9200 8200 8000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions