Select the correct statement about the use of Earned Value Management (EVM) data to support decision-making. EVM data doesnt help Program Managers (PMs) identify solutions

Select the correct statement about the use of Earned Value Management (EVM) data to support decision-making.
EVM data doesnt help Program Managers (PMs) identify solutions to problems, it merely reports the status of cost and schedule variances.
EVM data provides updated estimates at completion, but they are usually received too late to affect budget submissions
EVM data can give the program manager (PM) early insight into cost and schedule performance issues, giving PMs more time to implement mitigation activities that might improve performance.

Integrated analysis using EVM data is done to document contract performance, but contractors dont use it to take management action to mitigate problems.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Markets And Institutions

Authors: Frederic S. Mishkin, Stanley G. Eakins

9th Edition

0134519264, 9780134519265

More Books

Students also viewed these Finance questions