Selected information from the Blake Corporation accounting records for June follows: Materials Inventory BB (6/1) 91,000 463,000 418,000 Work-In-Process Inventory Labor 360,000 EB(6/30) 560,000 Finished
Selected information from the Blake Corporation accounting records for June follows:
Materials Inventory | ||||
BB (6/1) | 91,000 | |||
463,000 | 418,000 | |||
Work-In-Process Inventory | ||||
Labor | 360,000 | |||
EB(6/30) | 560,000 | |||
Finished Goods Inventory | ||||
BB (6/1) | 293,000 | |||
838,000 | 835,000 | |||
Cost of Goods Sold | ||||
26,000 | ||||
Manufacturing Overhead Control | ||||
370,000 | ||||
370,000 | ||||
Applied Manufacturing Overhead | ||||
396,000 | ||||
370,000 | ||||
26,000 |
Additional information for June follows:
Labor wage rate was $20 per hour.
During the month, sales revenue was $1,033,000, and selling and administrative costs were $238,000.
This company has no indirect materials or supplies.
The company applies manufacturing overhead on the basis of direct labor-hours.
Required:
a. What was the cost of direct materials purchased in June?
b. What was the over- or underapplied manufacturing overhead for June?
c. What was the manufacturing overhead application rate in June?
d. What was the cost of products completed during June?
e. What was the balance of the Work-in-Process Inventory account at the beginning of June?
f. What was the operating profit (or loss) for June? (Negative amounts should be indicated by a minus sign.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started