Question
Selection 1: Portland Cement Concrete Pavement The initial construction cost = RM 3,600,000 Cost for sealing connection (in year 10, 20 & 30) = RM
Selection 1: Portland Cement Concrete Pavement The initial construction cost = RM 3,600,000 Cost for sealing connection (in year 10, 20 & 30) = RM 123,000 Yearly scheduled maintenance = RM 54,000 The residual value of the pavement= RM 420,000
Selection 2: Hot-Mix Asphalt The initial construction cost = RM 2,700,000 Construction of Phase II (in year 10) = RM 1,050,000 Improvement of pavement (in year 15 & 30) = RM 870,000 Yearly scheduled maintenance = RM3,000 The residual value of the pavement =RM 840,000
Based on the above data, determine the best option for a road asset. The expected life span is 35 years for each selection. Given discount rate is 4% per annum.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started