Question

1 Approved Answer

Semi-automatic mixers are used to mix a particular chemical. It takes 5 minutes to charge a mixer; The mixer works automatically and produces a 1000-gallon

Semi-automatic mixers are used to mix a particular chemical. It takes 5 minutes to charge a mixer; The mixer works automatically and produces a 1000-gallon batch of chemicals before automatically discharging it. The automatic mixing time is 60 minutes. The automatic download time is 4 minutes. The journey between machines requires 15 seconds. While the mixers automatically mix the chemicals, the operator performs a quality control inspection on the previous bath, which requires 5 minutes per batch. An operator costs $15 per hour; each mixer costs $80 per hour.

(a) Determine the number of mixers that will be assigned per operator to minimize the cost per batch produced.

(b) Suppose there are 15 mixers to be allocated. How should they be allocated to minimize the long-run cost per lot?

(c) For what range of inspection time will the optimal number of mixers per operator be 7?

Step by Step Solution

3.39 Rating (158 Votes )

There are 3 Steps involved in it

Step: 1

a Determine the number of mixers that will be assigned per operator to minimize the cost per batch produced Lets denote N Number of mixers per operato... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Smith and Roberson Business Law

Authors: Richard A. Mann, Barry S. Roberts

15th Edition

1285141903, 1285141903, 9781285141909, 978-0538473637

More Books

Students also viewed these General Management questions

Question

Recall some characteristics of creative, divergent thinking.

Answered: 1 week ago