Seved Help Save & ENIE A job was budgeted to require 5 hours of labor per unit at $11.00 per hour The job consisted of
Seved Help Save & ENIE A job was budgeted to require 5 hours of labor per unit at $11.00 per hour The job consisted of 8 500 units and was completed in 40 500 hours at a total labor cost of $469 800 What is the total labor cost variance? Multiple Choice $2.300 unfavorable $6,024 unfavorable $3,724 unfavorable $460 unfavorable $8.500 unfavorable to search SA SUNDA