Seved Help The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June. Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Direct materials Direct labor Overhead Job 602 $1,500 800 480 Job 603 $3,400 1,560 936 Job 604 $3,200 1,600 960 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $600; direct labor, $250 and overhead, $150. Jobs 603 and 604 were started in June. Overhead cost is applied with a predetermined rate based on direct labor costs. Jobs 602 and 603 are finished in June, and Job 604 is expected to be finished in July. No raw materials are used indirectly in June. (Assume this company's predetermined overhead rate did not change over these months.) Required: 1. What is the cost of the raw materials used in June for each of the three jobs and in total? 2. How much total direct labor cost is incurred in June? 3. What predetermined overhead rate is used in June? 4. How much cost is transferred to finished goods inventory in June? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What is the cost of the raw materials used in June for each of the three jobs and in total? Job 802 Job 603 Job 604 Total May costs June costs Total $ 2,700 Romea 1 Required 2) 34 of 34 Next saved Job 602 was started in production in May, and these costs were assigned to it in May, direct materials, $600: direct labor, $250; ar overhead, $150. Jobs 603 and 604 were started in June. Overhead cost is applied with a predetermined rate based on direct labo costs. Jobs 602 and 603 are finished in June, and Job 604 is expected to be finished in July. No raw materials are used indirectly June. (Assume this company's predetermined overhead rate did not change over these months.) Required: 1. What is the cost of the raw materials used in June for each of the three jobs and in total? 2. How much total direct labor cost is incurred in June? 3. What predetermined overhead rate is used in June? 4. How much cost is transferred to finished goods inventory in June? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Total How much total direct labor cost is incurred in June? Job 602 Job 603 Job 604 May costs June costs Total + 01:01:39 Jellodu Tale did not change over these months.) Required: 1. What is the cost of the raw materials used in June for each of the three jobs and in total? 2. How much total direct labor cost is incurred in June? 3. What predetermined overhead rate is used in June? 4. How much cost is transferred to finished goods inventory in June? Complete this question by ente?ing your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What predetermined overhead rate is used in June? Predetermined overhead rate BB Seved Help The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the end of June. Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs. Direct materials Direct labor Overhead Job 602 $1,500 800 480 Job 603 $3,400 1,560 936 Job 604 $3,200 1,600 960 Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $600; direct labor, $250 and overhead, $150. Jobs 603 and 604 were started in June. Overhead cost is applied with a predetermined rate based on direct labor costs. Jobs 602 and 603 are finished in June, and Job 604 is expected to be finished in July. No raw materials are used indirectly in June. (Assume this company's predetermined overhead rate did not change over these months.) Required: 1. What is the cost of the raw materials used in June for each of the three jobs and in total? 2. How much total direct labor cost is incurred in June? 3. What predetermined overhead rate is used in June? 4. How much cost is transferred to finished goods inventory in June? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What is the cost of the raw materials used in June for each of the three jobs and in total? Job 802 Job 603 Job 604 Total May costs June costs Total $ 2,700 Romea 1 Required 2) 34 of 34 Next saved Job 602 was started in production in May, and these costs were assigned to it in May, direct materials, $600: direct labor, $250; ar overhead, $150. Jobs 603 and 604 were started in June. Overhead cost is applied with a predetermined rate based on direct labo costs. Jobs 602 and 603 are finished in June, and Job 604 is expected to be finished in July. No raw materials are used indirectly June. (Assume this company's predetermined overhead rate did not change over these months.) Required: 1. What is the cost of the raw materials used in June for each of the three jobs and in total? 2. How much total direct labor cost is incurred in June? 3. What predetermined overhead rate is used in June? 4. How much cost is transferred to finished goods inventory in June? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 Total How much total direct labor cost is incurred in June? Job 602 Job 603 Job 604 May costs June costs Total + 01:01:39 Jellodu Tale did not change over these months.) Required: 1. What is the cost of the raw materials used in June for each of the three jobs and in total? 2. How much total direct labor cost is incurred in June? 3. What predetermined overhead rate is used in June? 4. How much cost is transferred to finished goods inventory in June? Complete this question by ente?ing your answers in the tabs below. Required 1 Required 2 Required 3 Required 4 What predetermined overhead rate is used in June? Predetermined overhead rate BB